Search

Code Detail
Code No. KGS FU433 2022 Classification Gas facilities
Code Title Code for Facilities, Technology and Inspection for Installations Using LP Gas in Storage Tanks
Revised Date 2022.11.04 Price 117 USD,  111 Euro

Detail Information

Scope

1.1 Scope
This Code applies to the facilities, technology and inspection for installations using LP gas in
storage tanks among installations using LP gas in conformity to the Safety Control and Business
of Liquefied Petroleum Gas Act (hereinafter referred to as “Act”), Article 44, Clause 1. <Revised on October 2, 2015>

Contents

1. General........................................................................................................................................................................................1
1.1 Scope................................................................................................................................................................................1
1.2 Validity of Code...........................................................................................................................................................1
1.3 Definitions......................................................................................................................................................................1
1.4 Application of Codes (currently not used) .....................................................................................................6
1.5 Interim Measures........................................................................................................................................................6
1.5.1 Interim measure for installation standard for safety devices ...................................................6
1.5.2 Interim measure for installation standard for water spray systems ......................................6
1.5.3 Interim measure for standard for heat resisting construction and cooling sprinkler
systems, etc. for storage tanks .........................................................................................................................6
1.5.4 Interim measure for calculation of thickness and materials of piping.................................7
1.5.5 Interim measure for installation of piping.........................................................................................7
1.5.6 Interim measure for standard for installation of gas boilers....................................................8
1.5.7 Interim measure for gas burning facilities for dry sauna rooms <Newly established on November 26, 2009>.......................................................................................................................................8
1.5.8 Interim measure for Installation of underground storage tank rooms <Newly established on January 3, 2011> ......................................................................................................................9
1.5.10 Interim measure for fixation of storage tanks <Newly established on July 27, 2011>
...........................................................................................................................................................................................9
1.5.11 Interim measure for protection measures for storage facilities <Newly established on June 26, 2012> ...................................................................................................................................................9
1.5.12 Interim measure for prohibition of installation of open type hot water heaters
<Newly established on June 26, 2012> ........................................................................................................9
1.5.13 Interim measure for installation of combined type exhaust tubes of boilers
<Deleted><Newly established on June 26, 2012><Revised on September 29, 2017> ..... 10
1.5.14 Interim measure for installation of safety valve tail pipes <!-- Not Allowed Tag Filtered --><Newly established on June 26, 2012> ....................................................................................................................................................... 10
1.5.15 Interim measure for installation of gas